1. SS dependency implies?
The work can happen in parallel and the tasks must end at the same time.
The work can overlap or proceed in parallel.
Task 1 must finish before Task 2 can start
Task 2 must finish before Task 1 can start
2. A process that states how formal verfication and acceptance of completed project deliverables will be obtained is documented in the _________.
Procurement Management Plan
Quality Management Plan
Scope Management Plan
Commucations Management Plan
3. When adding a resource to a task, to only use them fifty percent, type this:
Bob[50]
Bob[.50]
Bob(.50)
Bob*.50
4. If you want to sort your resources by last name so that Brenda Diaz is last on your list and Florian Voss is first on your list, what sort order should you specify?
Descending
Z-A
Ascending
A-Z
5. What is the smallest denomination of time that can be assigned when assigning duration to tasks?
Hours
Days
Seconds
Minutes
6. The _______ is used as a template for other calendars.
Task calendar
Project calendar
Resource calendar
Base calendar
7. How much should CPI and SPI be in a project ahead of schedule and costs?
CPI <1; SPI<1
CPI >1, SPI >1
CPI<1 : SPI>1
CPI>1 ;SPI<1
8. Which of the following is the best way to resolve an issue in which a resource is overallocated?
Removing that resource from another task
Changing the resource's availability from 50% to 100%
It cannot be resolved.
Adding another resource to the task
9. If current data consistently differs from baseline data, this is an indication that ___
your actual data must be incorrect.
you must rework your baseline.
your original plan was never accurate.
your original plan is no longer accurate.
10. One of these is NOT a type of resource?
Schedule
Material
Work
Cost
11. The Network Diagram, also known as the ______, shows dependencies between tasks in a graphical manner.
Resource Graph
Timeline
PERT Chart
Gantt Chart
12. SF dependency implies?
Task 2 must finish before Task 1 can start
Task 1 must finish before Task 2 can start
The work can happen in parallel and the tasks must end at the same time.
The work can overlap or proceed in parallel
13. You have to deliver a new costume sales website by September 30 in time for the Halloween season that begins in mid-October. This is an example of?
Project Scheduling
Project Constraints
Critical Success Factor
Deadline
14. What is a Scope Manangement plan?
Plan that defines the procurement requirements for the project and how it will be managed from developing procurement documentation through contract closure.
Plan that documents the scope of communications between project participants, including outlining who is responsible for various types of information.
Plan that determines quality policies and procedures relevant to the project for both project deliverables and project processes, defines who is responsible for what, and documents compliance.
Plan that documents how the project purview will be defined documented verified managed and controlled by the Project Management team.
15. What does CPI of 1.1 mean ?
Project completed behind costs by 10%
Project schedule overrun by 1.1%
Project is completed ahead of costs by 10%
Project completed ahead of schedule by 10%
16. If you're not certain how Task "Chop the Wood" relates to the work of "Move the Chairs", which dependency type should you create?
SS
FS
SF
None of These
17. The ________ tab can be used to set working times, add a holiday to the calendar, and set a baseline.
Calendar
Resource
View
Project
18. The critical path method calculates theoretical early start and late start and finish dates. Critical path have either
Positive Total Float
Positive or Negative Total Float
Zero or Negative Total Float
Zero or Negative Total Float
19. To have Task 10 start three days after Task 9 completes, in the predecessor column, type:
T9+3
9FS3
All of these
9+3d
20. What is CPI=?
None of these
Earned Value /Actual Schedule
EV/AC
Actual Schedule/EV
21. Which of the following is NOT a valid task constraint?
FNLT - Finish no later than
FBTD - Finish by this dateMSO - Must start on
MSO - Must start on
ALAP - As late as possible
22. The default task type in Microsoft Project is ____.
fixed work
fixed units
fixed duration
fixed start
23. Use the ______ to see how changes to one task affect the rest of the project and to track schedule changes.
Resource Leveling
Task Inspector
Gantt Chart
Task Path Highlighting
24. After "Pour the Foundation" and "Build the Frame" are both finished, "Mount the Drywall" should start immediately. To put these task relationships in your plan, which dependency types should you create?
"Pour the Foundation" Finish-to-Finish with "Build the Frame," and "Mount the Drywall" Finish-to-Start with "Pour the Foundation."
Pour the Foundation" Start-to-Start with "Build the Frame," and "Mount the Drywall" Finish-to-Start with "Pour the Foundation."
"Pour the Foundation" Finish-to-Start with "Build the Frame," and "Build the Frame" Finish-to-Start with "Mount the Drywall"
Pour the Foundation" Finish-to-Start with "Build the Frame," and "Build the Frame" Finish-to-Start with "Mount the Drywall"
25. In manual scheduling, changes to which of the following updates task dates?
Project calendars
Constraints
None of the above
Task dependencies
26. ______ is an overlap between two tasks that are linked by a dependency.
Lag time
Slip
Lead time
Delayed start time
27. When two tasks have an FS dependency, but the work can overlap or be done in parallel, how can you reduce the overall duration of the project?
Change their dependency to SF
Change their dependency to FF
Move the deadline forward so that participants work faster.
Chance their dependency to SS
28. Microsoft Project allows up to ___ baselines per project.
100 11 2 1
11
2
1
29. Which of the following is NOT true of deadline dates?
Deadline dates can affect the total slack on tasks.
Deadline dates indicate a target date you don't want to miss.
Deadline dates affect task scheduling.
Deadline dates can be set on summary tasks and individual tasks.
30. When assigning a time duration to a task, what is the abbreviation for "months"?
mths
mos
mo
m
31. If a task is ______, as resources are added or removed on the assignment, the work remains constant and is redistributed among the resources.
ahead of schedule
effort-driven
work-driven
behind schedule
32. There are four tasks in your project, and the duration of your current plan is 22 days. There are FS dependencies between all four tasks. Task A is four days; Task B is six days; Task C is eight days; and Task D is four days. Which of the following changes will create a Project plan with the shortest overall duration?
Create a SF dependency between Task A and Task B.
Create a FF dependency between Task A and Task D
Create a SF dependency between Task C and Task D.
Create a SF dependency between Task B and Task C.
33. In a fixed units task, if you revise Duration, what happens?
Timelne is recalculated.
Dependencies are reassigned
Work is recalculated.
Units are recalculated.
34. On the Task tab, the _____ group provides buttons to mark the percent complete, link tasks to one another, and inactivate a task.
Task
Data
Properties
Schedule
35. Which of the following is NOT a risk-diagramming technique?
System Flowcharts
Control Diagram
Influence Diagrams
Cause and Effect Diagrams
36. You are the project manager on the rehab of an apartment building. Before you can get the Certificate of Occupancy, which is necessary to complete the project, the wiring must be installed. What type of precedence relationship is this?
Finish to Finish
Start to Finish
Start to Start
Finish to Start
37. ______ resources affect task scheduling.
Work and Cost
Work
Material
Work and material
38. What is the process of putting tasks in order of the date they must be completed by?
Nesting
Dating
Sequencing
Timing
39. To see all tasks for a person, which view should you look at?
Task usage
Resource sheet
Task sheet
Resource usage
40. To see individual resource details by task, which view should you look at?
Task usage
Resource usage
Task sheet
Resource sheet
41. A calendar can be associated with a:
Task
Resource and Project
All of these
Project
42. What is the most accurate way of forecasing EAC and ETC?
ETC based on New Estimates
ETC based on based on Atypical Variances
Earned Value
ETC based on Typical Variances
43. What is a variance thresshold for cost or other acceptable variances called?
Acceptable Thresshold
Variance Limit
Control Thresshold
Cost Limit
44. The __________ dialog box allows you select up to three fields for three levels of sorts within sorts.
sort
project information
group
None of these
45. What is another name for a summary task?
Hammock task
Overview task
Upper task
High-level task
46. Where can you set fixed duration, effort driven, and manually scheduled?
Team Planner
Resource Sheet
Project Information dialog box
Task form
47. You would like the ability to edit your typed entries in the Entry Bar, which appears below the ribbon and above the default Entry table in the Gantt Chart view. You recently received a new computer and noticed that the Entry Bar is missing. How do you fix this?
Use the Display tab in the Project Options dialog box to enable the Entry Bar.
Change the from Gantt Chart view to Tracking Gantt view.
Use the Advanced tab in the Project Options dialog box to enable the Entry Bar.
On the View tab on the ribbon, in the Split View group, select Details.
48. When setting the Calculate multiple critical paths option in a master project's Advanced settings, which statement is correct?
Subprojects will have critical paths calculated individually.
Individual resources will have critical paths calculated.
Milestones will have critical paths fixed.
Only one critical path will be calculated for a linked project.
49. You want to switch the scheduling mode for a project from scheduling from a start date to scheduling from a finish date. This action will change the default constraint from As Soon As Possible to As Late As Possible. Which dialog box should you use to make this change?
Resource Information
Project Information
Task Information
Change Working Time
50. A project contains many elements. What is used to describe the sum of the work required?
Task links
Resource Sheet
Work breakdown structure
Baseline
51. Which option is not available in the Report tab on the ribbon?
New Report
Network Diagram
Recent
Custom
52. You are troubleshooting a schedule on someone else's computer The schedule has 10,000 tasks. When a change is made to a task's duration on a Fixed Units task, the start and finish dates do not change. change highlighting does not appear, and the Gantt Chart bat does not update. What is the cause of this issue?
Inserted projects are calculated like summary tasks is selected.
Calculate multiple critical paths is not selected.
One of the Com add-ins is not selected.
Calculate project after each edit is set to Off.
53. You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?
Critical tasks are indicated in red and other tasks are indicated in blue.
Critical tasks are indicated in dark blue end other tasks are indicated in light blue.
Critical tasks are indicated in a report while the Gantt chart indicates all tasks in blue.
Critical tasks are indicated with an icon and other tasks are indicated in blue.
54. You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?
Must Finish On
Start No Earlier Than
As Soon As Possible
Finish No Earlier Than
55. Microsoft Project uses calendars to schedule a project. Which project components can be assigned a calendar?
Tasks and work
Work and units
Resources and work
Tasks and resources
56. You are working on a project file that contains many linked subprojects. When saving the files, what option can you use to immediately save the open files, including those that have not changed?
Yes to All
Yes
Save As
Save
57. A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?
It has changed to 10h.
It has changed to 6h.
It has changed to 125%.
It has changed to 110%.
58. What is another name for a work breakdown structure?
A hierarchy of tasks
A linking of tasks
A duration of tasks
A leveling of tasks