🧪 Microsoft Flow MCQ Quiz Hub

Microsoft Project MCQ Set 1

Choose a topic to test your knowledge and improve your Microsoft Flow skills

1. You are working on a project schedule. You need two tasks to end at the same time so that your review team can do their work on both tasks. Which link type is appropriate?




2. What does the Resource View display?




3. What does PERT stand for?




4. How does Microsoft Project calculate work?




5. The ______ tab on the ribbon allows you to customize text, columns, colors, and other elements of each type of view.




6. Which of the following is NOT a valid duration measurement for a task?




7. A project template has this file extension:




8. MS project is NOT interoperable with:




9. What is a successor activity?




10. A _________ is a deliverable oriented decomposition of a project into smaller components.




11. How many nested levels of sort criteria are available in the Sort dialog box?




12. A resource can be created by:




13. Which of the following is a valid task link type?




14. What is a milestone?




15. ______ is any deviation from the baseline of a project.




16. ___ are scheduled events that indicate the completion of a major deliverable.




17. By default, Duration is measured in:




18. What is a run chart?




19. Which of the following is NOT a standard field contained within a project?




20. What is the default duration assigned to an automatically scheduled task?




21. What is the default unit of time by which Lag Time is measured?




22. FS dependency implies?




23. How do you mark or indicate a task is a subtask of another?




24. ___ is a delay between two tasks that are linked by a dependency.




25. The _______ is the longest duration of linked tasks in a project which must be completed on time for the project to complete on time.




26. FF dependency implies?




27. Payback period is the time it takes to pay back what a project costs. For a project that costs $5,000,000 and delivers increased revenue of $500,000/month, how do you calcuate payback period?




28. The ______ view, automatically displayed above other views, shows a concise overview of the entire schedule.




29. What does PMI stand for?




30. ___ scheduling starts at the end of the project and works backwards through the project tasks to the present.




31. Which of the following is NOT a valid import type for tasks?




32. The __________ is the approved project schedule and issued to determine the variation between the plan and actual.




33. You are the project manager on the installation of a new ERP system. Before the system can be installed on the company's servers, the operating system must be upgraded. This is an example of what type of precedence relationship?




34. How does Microsoft Project calculate the total work time of a summary task?




35. Breaking a project into phases and then further dividing into summary tasks and subtasks is called _________ scheduling.




36. How will a task appear on the Gantt chart when it is a successor of another task?




37. What is the best way of doing resource loading in a project having lot of dependencies?




38. How can you change the duration on a summary task?




39. Putting 9FF3 in the predecessor column of task 10 causes which of the following to happen?




40. A _______ is a chart with a series of horizontal lines showing the amount of work done in certain periods of time in relation to the amount of work planned for those periods.




41. Use the _____ feature to resolve resource conflicts and over-allocations.




42. Press the ____ key to display KeyTips over each feature.




43. What is a Gantt chart?




44. What does WBS stand for?




45. The formula to calculate Cost Variance is:




46. Which of the following is NOT a constraint type?




47. The ________ new feature in Microsoft Project 2013 allows you to select any task and see the complete chain of predecessors and successors linked to it.




48. What does leveling refer to?




49. _______ is the length of time by which a task is ahead of schedule and will be completed early if continued.




50. What character follows an estimated duration?