SS dependency implies?
A process that states how formal verfication and acceptance of completed project deliverables will be obtained is documented in the _________.
When adding a resource to a task, to only use them fifty percent, type this:
If you want to sort your resources by last name so that Brenda Diaz is last on your list and Florian Voss is first on your list, what sort order should you specify?
What is the smallest denomination of time that can be assigned when assigning duration to tasks?
The _______ is used as a template for other calendars.
How much should CPI and SPI be in a project ahead of schedule and costs?
Which of the following is the best way to resolve an issue in which a resource is overallocated?
If current data consistently differs from baseline data, this is an indication that ___
One of these is NOT a type of resource?
The Network Diagram, also known as the ______, shows dependencies between tasks in a graphical manner.
SF dependency implies?
You have to deliver a new costume sales website by September 30 in time for the Halloween season that begins in mid-October. This is an example of?
What is a Scope Manangement plan?
What does CPI of 1.1 mean ?
If you're not certain how Task "Chop the Wood" relates to the work of "Move the Chairs", which dependency type should you create?
The ________ tab can be used to set working times, add a holiday to the calendar, and set a baseline.
The critical path method calculates theoretical early start and late start and finish dates. Critical path have either
To have Task 10 start three days after Task 9 completes, in the predecessor column, type:
What is CPI=?
Which of the following is NOT a valid task constraint?
The default task type in Microsoft Project is ____.
Use the ______ to see how changes to one task affect the rest of the project and to track schedule changes.
After "Pour the Foundation" and "Build the Frame" are both finished, "Mount the Drywall" should start immediately. To put these task relationships in your plan, which dependency types should you create?
In manual scheduling, changes to which of the following updates task dates?
______ is an overlap between two tasks that are linked by a dependency.
When two tasks have an FS dependency, but the work can overlap or be done in parallel, how can you reduce the overall duration of the project?
Microsoft Project allows up to ___ baselines per project.
Which of the following is NOT true of deadline dates?
When assigning a time duration to a task, what is the abbreviation for "months"?
If a task is ______, as resources are added or removed on the assignment, the work remains constant and is redistributed among the resources.
There are four tasks in your project, and the duration of your current plan is 22 days. There are FS dependencies between all four tasks. Task A is four days; Task B is six days; Task C is eight days; and Task D is four days. Which of the following changes will create a Project plan with the shortest overall duration?
In a fixed units task, if you revise Duration, what happens?
On the Task tab, the _____ group provides buttons to mark the percent complete, link tasks to one another, and inactivate a task.
Which of the following is NOT a risk-diagramming technique?
You are the project manager on the rehab of an apartment building. Before you can get the Certificate of Occupancy, which is necessary to complete the project, the wiring must be installed. What type of precedence relationship is this?
______ resources affect task scheduling.
What is the process of putting tasks in order of the date they must be completed by?
To see all tasks for a person, which view should you look at?
To see individual resource details by task, which view should you look at?
A calendar can be associated with a:
What is the most accurate way of forecasing EAC and ETC?
What is a variance thresshold for cost or other acceptable variances called?
The __________ dialog box allows you select up to three fields for three levels of sorts within sorts.
What is another name for a summary task?
Where can you set fixed duration, effort driven, and manually scheduled?
You would like the ability to edit your typed entries in the Entry Bar, which appears below the ribbon and above the default Entry table in the Gantt Chart view. You recently received a new computer and noticed that the Entry Bar is missing. How do you fix this?
When setting the Calculate multiple critical paths option in a master project's Advanced settings, which statement is correct?
You want to switch the scheduling mode for a project from scheduling from a start date to scheduling from a finish date. This action will change the default constraint from As Soon As Possible to As Late As Possible. Which dialog box should you use to make this change?
A project contains many elements. What is used to describe the sum of the work required?
Which option is not available in the Report tab on the ribbon?
You are troubleshooting a schedule on someone else's computer The schedule has 10,000 tasks. When a change is made to a task's duration on a Fixed Units task, the start and finish dates do not change. change highlighting does not appear, and the Gantt Chart bat does not update. What is the cause of this issue?
You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?
You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?
Microsoft Project uses calendars to schedule a project. Which project components can be assigned a calendar?
You are working on a project file that contains many linked subprojects. When saving the files, what option can you use to immediately save the open files, including those that have not changed?
A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?
What is another name for a work breakdown structure?