SS dependency implies?





โœ… Correct Answer: 2

A process that states how formal verfication and acceptance of completed project deliverables will be obtained is documented in the _________.





โœ… Correct Answer: 3

When adding a resource to a task, to only use them fifty percent, type this:





โœ… Correct Answer: 1

If you want to sort your resources by last name so that Brenda Diaz is last on your list and Florian Voss is first on your list, what sort order should you specify?





โœ… Correct Answer: 1

What is the smallest denomination of time that can be assigned when assigning duration to tasks?





โœ… Correct Answer: 4

The _______ is used as a template for other calendars.





โœ… Correct Answer: 1

How much should CPI and SPI be in a project ahead of schedule and costs?





โœ… Correct Answer: 2

Which of the following is the best way to resolve an issue in which a resource is overallocated?





โœ… Correct Answer: 2

If current data consistently differs from baseline data, this is an indication that ___





โœ… Correct Answer: 4

One of these is NOT a type of resource?





โœ… Correct Answer: 1

The Network Diagram, also known as the ______, shows dependencies between tasks in a graphical manner.





โœ… Correct Answer: 3

SF dependency implies?





โœ… Correct Answer: 1

You have to deliver a new costume sales website by September 30 in time for the Halloween season that begins in mid-October. This is an example of?





โœ… Correct Answer: 2

What is a Scope Manangement plan?





โœ… Correct Answer: 4

What does CPI of 1.1 mean ?





โœ… Correct Answer: 3

If you're not certain how Task "Chop the Wood" relates to the work of "Move the Chairs", which dependency type should you create?





โœ… Correct Answer: 2

The ________ tab can be used to set working times, add a holiday to the calendar, and set a baseline.





โœ… Correct Answer: 4

The critical path method calculates theoretical early start and late start and finish dates. Critical path have either





โœ… Correct Answer: 2

To have Task 10 start three days after Task 9 completes, in the predecessor column, type:





โœ… Correct Answer: 2

What is CPI=?





โœ… Correct Answer: 3

Which of the following is NOT a valid task constraint?





โœ… Correct Answer: 2

The default task type in Microsoft Project is ____.





โœ… Correct Answer: 2

Use the ______ to see how changes to one task affect the rest of the project and to track schedule changes.





โœ… Correct Answer: 2

After "Pour the Foundation" and "Build the Frame" are both finished, "Mount the Drywall" should start immediately. To put these task relationships in your plan, which dependency types should you create?





โœ… Correct Answer: 1

In manual scheduling, changes to which of the following updates task dates?





โœ… Correct Answer: 3

______ is an overlap between two tasks that are linked by a dependency.





โœ… Correct Answer: 3

When two tasks have an FS dependency, but the work can overlap or be done in parallel, how can you reduce the overall duration of the project?





โœ… Correct Answer: 2

Microsoft Project allows up to ___ baselines per project.





โœ… Correct Answer: 2

Which of the following is NOT true of deadline dates?





โœ… Correct Answer: 3

When assigning a time duration to a task, what is the abbreviation for "months"?





โœ… Correct Answer: 3

If a task is ______, as resources are added or removed on the assignment, the work remains constant and is redistributed among the resources.





โœ… Correct Answer: 2

There are four tasks in your project, and the duration of your current plan is 22 days. There are FS dependencies between all four tasks. Task A is four days; Task B is six days; Task C is eight days; and Task D is four days. Which of the following changes will create a Project plan with the shortest overall duration?





โœ… Correct Answer: 3

In a fixed units task, if you revise Duration, what happens?





โœ… Correct Answer: 3

On the Task tab, the _____ group provides buttons to mark the percent complete, link tasks to one another, and inactivate a task.





โœ… Correct Answer: 4

Which of the following is NOT a risk-diagramming technique?





โœ… Correct Answer: 2

You are the project manager on the rehab of an apartment building. Before you can get the Certificate of Occupancy, which is necessary to complete the project, the wiring must be installed. What type of precedence relationship is this?





โœ… Correct Answer: 1

______ resources affect task scheduling.





โœ… Correct Answer: 2

What is the process of putting tasks in order of the date they must be completed by?





โœ… Correct Answer: 1

To see all tasks for a person, which view should you look at?





โœ… Correct Answer: 4

To see individual resource details by task, which view should you look at?





โœ… Correct Answer: 1

A calendar can be associated with a:





โœ… Correct Answer: 2

What is the most accurate way of forecasing EAC and ETC?





โœ… Correct Answer: 1

What is a variance thresshold for cost or other acceptable variances called?





โœ… Correct Answer: 3

The __________ dialog box allows you select up to three fields for three levels of sorts within sorts.





โœ… Correct Answer: 1

What is another name for a summary task?





โœ… Correct Answer: 1

Where can you set fixed duration, effort driven, and manually scheduled?





โœ… Correct Answer: 4

You would like the ability to edit your typed entries in the Entry Bar, which appears below the ribbon and above the default Entry table in the Gantt Chart view. You recently received a new computer and noticed that the Entry Bar is missing. How do you fix this?





โœ… Correct Answer: 1

When setting the Calculate multiple critical paths option in a master project's Advanced settings, which statement is correct?





โœ… Correct Answer: 1

You want to switch the scheduling mode for a project from scheduling from a start date to scheduling from a finish date. This action will change the default constraint from As Soon As Possible to As Late As Possible. Which dialog box should you use to make this change?





โœ… Correct Answer: 2

A project contains many elements. What is used to describe the sum of the work required?





โœ… Correct Answer: 3

Which option is not available in the Report tab on the ribbon?





โœ… Correct Answer: 2

You are troubleshooting a schedule on someone else's computer The schedule has 10,000 tasks. When a change is made to a task's duration on a Fixed Units task, the start and finish dates do not change. change highlighting does not appear, and the Gantt Chart bat does not update. What is the cause of this issue?





โœ… Correct Answer: 4

You would like to understand which tasks are critical and which are not. When looking at the Gantt chart, how are these tasks identified by default?





โœ… Correct Answer: 1

You are working on a project that has tasks with no flexibility. Which constraint type offers no flexibility?





โœ… Correct Answer: 1

Microsoft Project uses calendars to schedule a project. Which project components can be assigned a calendar?





โœ… Correct Answer: 1

You are working on a project file that contains many linked subprojects. When saving the files, what option can you use to immediately save the open files, including those that have not changed?





โœ… Correct Answer: 1

A resource is assigned to a task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h) per day at 100%. The resource performs actual work of 10 hours on the first day. How has the Peak for this resource changed?





โœ… Correct Answer: 3

What is another name for a work breakdown structure?





โœ… Correct Answer: 1